Work will soon begin on the Wellington elevated water storage tank.
Council awarded the contract to Landmark Structures Co. on Tuesday night during their regular council meeting for the construction of an elevated water storage tank and bulk water filling station at a cost of $9,002,000.
This is over-budget by almost $1 million and the budget increase of $992,772.15 will be funded by long-term debt.
Council also approved a contract to CIMA Canada Inc. for the Wellington water treatment plan, wastewater treatment plant and regional water supply class environmental assessments at a cost of $402,868.